Sunergy, Inc.: OSHA inspection records

Data as of November 16, 2026

$17,235initial (proposed) penalties

5 alleged violation items across 1 cited inspection in the last 12 months, including 1 serious.

Status1 contestedinspection status per the public record

Get California alerts
Location
1249 Camino Prado, Chula Vista, CA 91913
Industry
Utilities (NAICS 221114, Electric Power Generation, Transmission and Distribution)
Jurisdiction
California, State plan
Cited inspections
1 in the last 12 months

Alleged violations. Citations issued by a State Plan office. Citations are allegations with proposed penalties until they become final orders; each record shows its status label, initial and current penalty as of November 16, 2026. About this data · Methodology

Official records: each osha.gov link opens the official record, next to its inspection number. If osha.gov asks you to verify you're human and then shows its homepage, search that number at OSHA's Establishment Search.

Inspection 348550542

Contested Under contest; not a final finding. Items and penalties may change.

$17,235Initial (proposed) penalty
$17,235Current penalty
5Alleged violation items
Opened
October 13, 2025
Citations issued
April 10, 2026
Abatement due
May 20, 2026 (per OSHA record)
Contest date
June 23, 2026 (per OSHA record)
Official record
osha.gov inspection detail #348550542 · OSHA Establishment Search (if osha.gov shows its homepage, search inspection 348550542)
CitationStandardTypeIssuedAbatement dueInitial penaltyCurrent penaltyStatus
Citation 0100143000040 AOther-than-seriousApr 10, 2026May 20, 2026$225$225Contested
Citation 010021509(A)Other-than-seriousApr 10, 2026May 20, 2026$420$420Contested
Citation 010031509(B)Other-than-seriousApr 10, 2026May 20, 2026$420$420Contested
Citation 010043395(I)Other-than-seriousApr 10, 2026May 20, 2026$420$420Contested
Citation 020011670(A)SeriousApr 10, 2026May 20, 2026$15,750$15,750Contested

Compared with similar employers

Among 28 other Electric Power Generation, Transmission and Distribution (NAICS 2211) establishments in California with citations issued in the last 12 months, this establishment's proposed penalties ($17,235) were higher than 64% of them, and its 5 alleged items more than 93%.

Last 12 monthsThis establishmentPeer medianHigher than
Initial (proposed) penalties$17,235$11,73564%
Alleged violation items5393%
Peers: cited establishments in the same NAICS industry in California. Proposed penalties before any settlement.

Standards cited most in this industry

Share of the 135 cited inspections in Electric Power Generation, Transmission and Distribution (NAICS 2211) nationwide (last 12 months) that included each standard.

StandardTopicShare of inspectionsCited here
1910.269Electric Power Work19%
1926.501Fall Protection8%
1910.303Electrical General7%
1910.212Machine Guarding4%
1926.503Fall Protection Training4%
1910.1200Hazard Communication3%

Other utilities employers cited in California