Minnesota OSHA citations issued the week of Feb 16, 2026
Week of Feb 16, 2026 · data as of October 5, 2026
14 inspections in Minnesota had citations issued between Feb 16, 2026 and Feb 22, 2026, with 65 alleged violation items and $159,050 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
14inspections with citations issued
65alleged violation items
$159,050initial penalties
$146,560current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Wissota Promoters Association Inc. | Fergus Falls | Feb 20, 2026 | 6 | $57,250 | $57,250 | ContestedAbatement due Mar 2, 2026Contested Mar 11, 2026 | osha.gov | |
| ISD 182 - Crosby Ironton Senior High School | Crosby | Feb 20, 2026 | 1 | $1,200 | $1,200 | Final orderAbatement due Mar 10, 2026 | osha.gov | |
| Hagens Glass - Paint Inc. | Cloquet | Feb 20, 2026 | 3 | $1,200 | $720 | Informal settlementAbatement due Mar 5, 2026 | osha.gov | |
| UMC Inc. | Monticello | Feb 19, 2026 | 5 | $10,800 | $6,480 | Informal settlementAbatement due Feb 27, 2026 | osha.gov | |
| Tafco Equipment Co. | Blue Earth | Feb 19, 2026 | 7 | $9,600 | $9,600 | Final orderAbatement due Mar 9, 2026 | osha.gov | |
| The Scooper Company LLC dba Northwind Trailer GRP | Blooming Prairie | Feb 19, 2026 | 8 | $5,250 | $3,000 | Formal settlementAbatement due Sep 14, 2026Contested Feb 23, 2026 | osha.gov | |
| Kraemer Lumber Co. Inc. | Melrose | Feb 19, 2026 | 7 | $2,850 | $1,710 | Informal settlementAbatement due Feb 25, 2026 | osha.gov | |
| Neufeldt Industrial Services Inc. | Red Wing | Feb 19, 2026 | 3 | $2,000 | $1,200 | Informal settlementAbatement due Mar 9, 2026 | osha.gov | |
| Oreilly Auto Enterprises LLC dba Oreilly Auto Part | Minneapolis | Feb 18, 2026 | 4 | $16,450 | $16,450 | Final orderAbatement due Feb 23, 2026 | osha.gov | |
| Dura-Supreme LLC | Howard Lake | Feb 18, 2026 | 5 | $11,900 | $8,400 | Formal settlementAbatement due Feb 23, 2026Contested Mar 10, 2026 | osha.gov | |
| NFD Hardware Inc. dba Northfield Ace Hardware | Northfield | Feb 18, 2026 | 3 | $1,250 | $1,250 | Final orderAbatement due Mar 2, 2026 | osha.gov | |
| Zbros Enterprise dba Redi-Haul Trailers | Fairmont | Feb 18, 2026 | 1 | $150 | $150 | Final orderAbatement due Feb 23, 2026 | osha.gov | |
| Elim Homes Inc. dba Elim Wellspring Assisted Living | Princeton | Feb 17, 2026 | 9 | $38,400 | $38,400 | ContestedAbatement due Feb 23, 2026Contested Mar 5, 2026 | osha.gov | |
| Tek Steel Fabricators Inc. | Bethel | Feb 17, 2026 | 3 | $750 | $750 | Final orderAbatement due Mar 6, 2026 | osha.gov |
Standards cited this week
- 1910.1200 Hazard Communication (5)
- 1910.305 Wiring Methods (4)
- 1910.134 Respiratory Protection (3)
- 1910.212 Machine Guarding (3)
- 1910.213 Woodworking Machinery (2)
- 1910.23 Ladders (2)
- 1910.132 PPE General Requirements (2)
- 1910.28 Fall Protection Duty (2)
- 1910.107 Spray Finishing (1)
- 1910.106 Flammable Liquids (1)
- 1910.1030 Bloodborne Pathogens (1)
- 1904.29 OSHA 300 and 301 Forms (1)