Washington OSHA citations issued the week of Aug 24, 2026
Week of Aug 24, 2026 · data as of November 16, 2026
85 inspections in Washington had citations issued between Aug 24, 2026 and Aug 30, 2026, with 290 alleged violation items and $256,110 in proposed penalties. Statuses and current penalties reflect the data as of November 16, 2026.
85inspections with citations issued
290alleged violation items
$256,110initial penalties
$241,475current penalties
Alleged violations. Citations are allegations with proposed penalties until they become final orders; each record shows its status label, initial and current penalty as of November 16, 2026. About this data · Methodology
Official records: each osha.gov link opens the official record, next to its inspection number. If osha.gov asks you to verify you're human and then shows its homepage, search that number at OSHA's Establishment Search.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Ginsing LLC | Seattle | Aug 28, 2026 | 7 | $15,411 | $15,411 | ContestedAbatement due Sep 20, 2026Contested Sep 18, 2026 | osha.gov #348968884 | |
| Sierra Custom Construction LLC | East Wenatchee | Aug 28, 2026 | 10 | $9,630 | $9,630 | OpenAbatement due Sep 20, 2026Contest deadline ~Sep 21, 2026 (est.) | osha.gov #348960253 | |
| Big Sky ID Corp. | Airway Heights | Aug 28, 2026 | 3 | $7,706 | $7,706 | Final orderAbatement due Sep 30, 2026 | osha.gov #348938754 | |
| Comfort IQ LLC | Kennewick | Aug 28, 2026 | 4 | $5,136 | $3,081 | Final orderContested Sep 3, 2026 | osha.gov #348963265 | |
| JFG Construction LLC | Shelton | Aug 28, 2026 | 5 | $3,852 | $3,852 | ContestedContested Oct 10, 2026 | osha.gov #348960311 | |
| Emerald Green Roofing LLC | Granite Falls | Aug 28, 2026 | 6 | $3,852 | $3,852 | OpenAbatement due Sep 15, 2026Contest deadline ~Sep 21, 2026 (est.) | osha.gov #348968991 | |
| CM Development & Construction LLC | Spokane Valley | Aug 28, 2026 | 6 | $3,852 | $3,852 | Final order | osha.gov #348924614 | |
| Meyers Metal Works Inc. | Arlington | Aug 28, 2026 | 7 | $2,568 | $2,568 | Final orderAbatement due Sep 15, 2026 | osha.gov #348968751 | |
| Aseptico Inc. | Woodinville | Aug 28, 2026 | 5 | $1,284 | $1,284 | Final orderAbatement due Sep 30, 2026 | osha.gov #348957598 | |
| Swenson Estate Holdings L L C | Renton | Aug 28, 2026 | 3 | $642 | $642 | ContestedContested Sep 21, 2026 | osha.gov #348927153 | |
| Rosemans LLC | Seattle | Aug 28, 2026 | 1 | $600 | $600 | Final order | osha.gov #349081059 | |
| Oso Creek LLC | Arlington | Aug 28, 2026 | 5 | $0 | $0 | Final orderAbatement due Sep 30, 2026 | osha.gov #348969049 | |
| Chinook Lumber Inc. | Snohomish | Aug 28, 2026 | 1 | $0 | $0 | Final order | osha.gov #348963141 | |
| Billy Burger LLC | Wilbur | Aug 28, 2026 | 4 | $0 | $0 | Final orderAbatement due Sep 30, 2026 | osha.gov #348963257 | |
| G I Trucking Co. | Tacoma | Aug 28, 2026 | 3 | $0 | $0 | Status not determinableAbatement due Sep 30, 2026 | osha.gov #348968843 | |
| City of Port Townsend | Port Townsend | Aug 27, 2026 | 3 | $6,422 | $6,422 | Final orderAbatement due Sep 29, 2026 | osha.gov #348957556 | |
| Pulsar Electric LLC | Union Gap | Aug 27, 2026 | 9 | $3,852 | $3,852 | ContestedContested Sep 14, 2026 | osha.gov #348957572 | |
| Nylatech Incorporated | Everson | Aug 27, 2026 | 5 | $3,852 | $3,852 | Final orderAbatement due Sep 4, 2026 | osha.gov #348949504 | |
| Name withheld (individual) | Yakima | Aug 27, 2026 | 4 | $2,889 | $2,889 | ContestedAbatement due Sep 14, 2026Contested Sep 3, 2026 | osha.gov #348954983 | |
| Ganoson Inc. | Marysville | Aug 27, 2026 | 2 | $1,926 | $1,926 | Final orderAbatement due Sep 29, 2026 | osha.gov #348954934 | |
| Bknd Inc. | Everett | Aug 27, 2026 | 4 | $1,284 | $1,284 | Final orderAbatement due Sep 4, 2026 | osha.gov #348952201 | |
| Valueglass LLC | Bremerton | Aug 27, 2026 | 2 | $0 | $0 | Final orderAbatement due Sep 29, 2026 | osha.gov #348957531 | |
| Vinyl Lab NW LLC | Everett | Aug 27, 2026 | 4 | $0 | $0 | Final orderAbatement due Sep 29, 2026 | osha.gov #348957481 | |
| Yonder Cider LLC | Wenatchee | Aug 27, 2026 | 4 | $0 | $0 | Final orderAbatement due Sep 9, 2026 | osha.gov #348963158 | |
| Stone Masters Inc. | Wenatchee | Aug 27, 2026 | 3 | $0 | $0 | OpenAbatement due Sep 19, 2026Contest deadline ~Sep 18, 2026 (est.) | osha.gov #348963166 | |
| Fusion Dining LLC | Grandview | Aug 27, 2026 | 1 | $0 | $0 | Final order | osha.gov #348949496 | |
| Macdonald Miller Facility Solutions LLC | Bellevue | Aug 26, 2026 | 2 | $5,780 | $5,780 | Final order | osha.gov #348957515 | |
| Three Lakes Electric LLC | Seattle | Aug 26, 2026 | 7 | $5,778 | $5,778 | OpenAbatement due Sep 13, 2026Contest deadline ~Sep 17, 2026 (est.) | osha.gov #348840737 | |
| Elite Fabrication & Constructi | Lakewood | Aug 26, 2026 | 6 | $5,350 | $5,350 | Final orderAbatement due Sep 13, 2026 | osha.gov #348916693 | |
| Outwest Cherry Orchards LLC | Mattawa | Aug 26, 2026 | 1 | $5,137 | $1,541 | Final orderAbatement due Sep 13, 2026Contested Sep 1, 2026 | osha.gov #348941659 | |
| Titus Will Hyundai Sales Inc. | Olympia | Aug 26, 2026 | 6 | $4,494 | $2,310 | Final orderAbatement due Sep 12, 2026Contested Sep 3, 2026 | osha.gov #348954900 | |
| Central Washington Asphalt Inc. | Prosser | Aug 26, 2026 | 1 | $3,853 | $3,853 | Final orderContested Sep 15, 2026 | osha.gov #348983446 | |
| Scafco Grain LLC | Spokane Valley | Aug 26, 2026 | 4 | $3,425 | $3,425 | Final orderAbatement due Sep 28, 2026 | osha.gov #348968868 | |
| Harts Plumbing & Excavation LLC | Kent | Aug 26, 2026 | 1 | $3,211 | $3,211 | ContestedContested Sep 14, 2026 | osha.gov #348949462 | |
| Sand Slope Acres Inc. | Othello | Aug 26, 2026 | 6 | $2,569 | $2,569 | Final orderAbatement due Sep 3, 2026 | osha.gov #348949470 | |
| INOV8V Marine Group Inc. | Arlington | Aug 26, 2026 | 4 | $2,568 | $2,568 | Final order | osha.gov #348946237 | |
| School Dist #409 King County | Maple Valley | Aug 26, 2026 | 2 | $2,140 | $2,140 | ContestedAbatement due Sep 28, 2026Contested Sep 9, 2026 | osha.gov #348978008 | |
| Tacomaspot LLC | Tacoma | Aug 26, 2026 | 6 | $642 | $642 | Final orderAbatement due Sep 19, 2026 | osha.gov #348952227 | |
| Klar Scientific Inc. | Pullman | Aug 26, 2026 | 1 | $0 | $0 | Final order | osha.gov #348911363 | |
| A Glass Enterprise Inc. | Centralia | Aug 26, 2026 | 5 | $0 | $0 | OpenAbatement due Sep 28, 2026Contest deadline ~Sep 17, 2026 (est.) | osha.gov #348957457 | |
| The Boeing Company | Everett | Aug 26, 2026 | 1 | $0 | $0 | ContestedAbatement due Sep 13, 2026Contested Sep 30, 2026 | osha.gov #348946260 | |
| Tacoma Abatement Company LLC | Winlock | Aug 26, 2026 | 2 | $0 | $0 | ContestedAbatement due Sep 8, 2026Contested Sep 4, 2026 | osha.gov #348960162 | |
| Clary Auburn VW LLC | Auburn | Aug 26, 2026 | 2 | $0 | $0 | Final orderAbatement due Oct 5, 2026 | osha.gov #348960212 | |
| AK Fitness LLC | Woodinville | Aug 26, 2026 | 2 | $0 | $0 | Final order | osha.gov #348971771 | |
| The Boeing Company | Auburn | Aug 25, 2026 | 2 | $14,126 | $14,126 | ContestedAbatement due Sep 12, 2026Contested Sep 23, 2026 | osha.gov #349029074 | |
| Integrity Traffic OR LLC | Centralia | Aug 25, 2026 | 1 | $11,558 | $11,558 | Final order | osha.gov #348941691 | |
| Kennedy Endeavors Llcorporated | Algona | Aug 25, 2026 | 4 | $8,562 | $8,562 | ContestedAbatement due Sep 27, 2026Contested Sep 18, 2026 | osha.gov #349007088 | |
| Boise Cascade Company | Kettle Falls | Aug 25, 2026 | 2 | $5,780 | $5,780 | Final orderAbatement due Sep 7, 2026 | osha.gov #348929449 | |
| J a T Roofing LLC | Pullman | Aug 25, 2026 | 6 | $5,736 | $5,736 | OpenAbatement due Sep 27, 2026Contest deadline ~Sep 16, 2026 (est.) | osha.gov #348924853 | |
| Harbor Alternate Living Associ | Aberdeen | Aug 25, 2026 | 3 | $3,854 | $3,854 | ContestedContested Sep 14, 2026 | osha.gov #348952193 | |
| Outwest Cherry Orchards LLC | Mattawa | Aug 25, 2026 | 10 | $3,211 | $1,541 | Final orderAbatement due Sep 2, 2026Contested Sep 1, 2026 | osha.gov #348938606 | |
| JS Meza Roofing LLC | Wenatchee | Aug 25, 2026 | 4 | $2,889 | $2,889 | ContestedAbatement due Sep 27, 2026Contested Sep 15, 2026 | osha.gov #348952276 | |
| Contech Services Inc. | Seattle | Aug 25, 2026 | 1 | $2,569 | $2,569 | ContestedContested Sep 15, 2026 | osha.gov #349011940 | |
| Pierce County Rural Library District | Tacoma | Aug 25, 2026 | 2 | $2,569 | $2,569 | ContestedAbatement due Oct 16, 2026Contested Sep 9, 2026 | osha.gov #348943820 | |
| Zirkle Fruit Co. | Prosser | Aug 25, 2026 | 1 | $1,927 | $1,927 | Final order | osha.gov #349042754 | |
| Name withheld (individual) | Ravensdale | Aug 25, 2026 | 1 | $1,926 | $1,926 | ContestedContested Sep 11, 2026 | osha.gov #348927120 | |
| Olsen Anderson Construction LLC | Seattle | Aug 25, 2026 | 4 | $1,284 | $1,284 | Final order | osha.gov #348938689 | |
| Name withheld (individual) | Ford | Aug 25, 2026 | 5 | $1,284 | $1,284 | ContestedAbatement due Sep 12, 2026Contested Sep 9, 2026 | osha.gov #348946294 | |
| Green Dreamer LLC | Bellingham | Aug 25, 2026 | 6 | $1,284 | $1,284 | ContestedContested Sep 14, 2026 | osha.gov #348941717 | |
| Addison Marie LLC | Ellensburg | Aug 25, 2026 | 2 | $1,284 | $1,284 | Final orderAbatement due Sep 21, 2026 | osha.gov #348952367 | |
| Aim Star Learning PLLC | Maple Valley | Aug 25, 2026 | 3 | $1,070 | $1,070 | ContestedAbatement due Sep 12, 2026Contested Sep 15, 2026 | osha.gov #348963182 | |
| Thang DO Construction LLC | Olympia | Aug 25, 2026 | 1 | $963 | $963 | Final order | osha.gov #348952441 | |
| Mindsource Center LLC | Maple Valley | Aug 25, 2026 | 3 | $856 | $856 | ContestedAbatement due Sep 12, 2026Contested Sep 14, 2026 | osha.gov #348963190 | |
| Name withheld (individual) | Wenatchee | Aug 25, 2026 | 2 | $642 | $642 | Final orderAbatement due Sep 27, 2026 | osha.gov #348952292 | |
| Bajwa Enterprise Corporation 1 | Westport | Aug 25, 2026 | 4 | $535 | $535 | Final order | osha.gov #348949520 | |
| North Auburn Care LLC | Auburn | Aug 25, 2026 | 2 | $0 | $0 | OpenAbatement due Sep 27, 2026Contest deadline ~Sep 16, 2026 (est.) | osha.gov #348968801 | |
| North Star Cold Storage Inc. | Stanwood | Aug 25, 2026 | 2 | $0 | $0 | Final orderAbatement due Sep 27, 2026 | osha.gov #348949587 | |
| Jays Garage | Seattle | Aug 25, 2026 | 1 | $0 | $0 | Final orderAbatement due Sep 27, 2026 | osha.gov #348952268 | |
| Young Womens Christian Assoc of Seattle King | Everett | Aug 25, 2026 | 5 | $0 | $0 | Status not determinableAbatement due Sep 27, 2026 | osha.gov #348952383 | |
| O & V Construction LLC | Mead | Aug 25, 2026 | 2 | $0 | $0 | Final order | osha.gov #348943903 | |
| Rickys General Construction LLC | Benton City | Aug 24, 2026 | 2 | $23,112 | $23,112 | ContestedContested Sep 3, 2026 | osha.gov #348938663 | |
| Vector Force Development LLC | Olympia | Aug 24, 2026 | 2 | $6,422 | $6,422 | ContestedContested Sep 4, 2026 | osha.gov #348952425 | |
| Lakewood Roofing LLC | Lakewood | Aug 24, 2026 | 2 | $6,420 | $6,420 | Final order | osha.gov #348983479 | |
| City of Liberty Lake | Liberty Lake | Aug 24, 2026 | 3 | $5,137 | $1,548 | Final orderAbatement due Sep 26, 2026Contested Sep 8, 2026 | osha.gov #348934787 | |
| Sci Infrastructure LLC | Bainbridge Island | Aug 24, 2026 | 3 | $4,818 | $4,818 | ContestedAbatement due Sep 26, 2026Contested Aug 26, 2026 | osha.gov #348919341 | |
| United States Bakery dba Franz Family Bakerie | Olympia | Aug 24, 2026 | 2 | $4,708 | $4,708 | Final orderAbatement due Sep 10, 2026 | osha.gov #348927054 | |
| Sandrini & Sons Construction | Toledo | Aug 24, 2026 | 6 | $3,852 | $2,311 | Final orderAbatement due Sep 11, 2026Contested Sep 8, 2026 | osha.gov #348952391 | |
| City of Shoreline | Shoreline | Aug 24, 2026 | 2 | $3,425 | $3,425 | Final orderAbatement due Sep 11, 2026 | osha.gov #348919226 | |
| Nippon Dynawave Packaging Co. | Longview | Aug 24, 2026 | 2 | $2,890 | $2,890 | Status not determinableAbatement due Sep 26, 2026 | osha.gov #348795717 | |
| Complete Heating & Sheet Metal Inc. | Spokane | Aug 24, 2026 | 4 | $1,712 | $1,712 | ContestedAbatement due Sep 26, 2026Contested Sep 4, 2026 | osha.gov #348952318 | |
| Extrahop Networks Inc. | Seattle | Aug 24, 2026 | 2 | $0 | $0 | Final orderAbatement due Oct 9, 2026 | osha.gov #349009720 | |
| Roanoke Excavation LLC | Asotin | Aug 24, 2026 | 5 | $0 | $0 | OpenAbatement due Sep 26, 2026Contest deadline ~Sep 15, 2026 (est.) | osha.gov #348957523 | |
| Kennedy Endeavors Llcorporated | Algona | Aug 24, 2026 | 2 | $0 | $0 | Final orderAbatement due Sep 26, 2026 | osha.gov #349070292 | |
| Capstone Construction Company | Spokane | Aug 24, 2026 | 3 | $0 | $0 | Final orderAbatement due Sep 26, 2026 | osha.gov #348949546 | |
| Pacific Beach Fresh Foods LLC | Pacific Beach | Aug 24, 2026 | 1 | $0 | $0 | Final order | osha.gov #348949413 |