MTZ Framing, LLC: OSHA inspection records
Data as of October 5, 2026
- Location
- 155 Proctor Street, East Boston, MA 02128
- Industry
- Construction (NAICS 238130)
- Jurisdiction
- Massachusetts, Federal OSHA
- Cited inspections
- 1 in the last 12 months
Alleged violations. The items below are citations issued by federal OSHA. They are allegations and proposed penalties, not findings of wrongdoing, unless and until they become final orders. Employers may contest citations or settle them, and items may be reduced, reclassified or withdrawn. The status label and the original and current penalties are taken from the public record as of October 5, 2026.
Inspection 348463415
Final order The citation items have become a final order.
$12,457Initial (proposed) penalty
$12,457Current penalty
7Alleged violation items
- Opened
- August 25, 2025
- Citations issued
- January 30, 2026 to June 11, 2026
- Abatement due
- March 23, 2026 to June 30, 2026 (per OSHA record)
- Final order date
- July 15, 2026 (per OSHA record)
- Official record
- osha.gov inspection detail 348463415
| Citation | Standard | Type | Issued | Abatement due | Initial penalty | Current penalty | Status |
|---|---|---|---|---|---|---|---|
| Citation 01001 | 1926.20(b)(2) Construction Safety Programs | Serious | Jan 30, 2026 | Mar 23, 2026 | $2,128 | $2,128 | Final order |
| Citation 01002 | 1926.34(b) Construction Exit Routes | Serious | Jan 30, 2026 | Mar 23, 2026 | $2,128 | $2,128 | Final order |
| Citation 01003 | 1926.150(a)(2) Construction Fire Protection | Serious | Jan 30, 2026 | — | $2,128 | $2,128 | Final order |
| Citation 01004 | 1926.150(c)(1)(iv) Construction Fire Protection | Serious | Jan 30, 2026 | — | $2,128 | $2,128 | Final order |
| Citation 01005A | 1926.502(b)(1) Fall Protection Systems | Serious | Jan 30, 2026 | — | $3,547 | $3,547 | Final order |
| Citation 01005B | 1926.502(i)(3) Fall Protection Systems | Serious | Jan 30, 2026 | — | $0 | $0 | Final order |
| Citation 02001 | 1903.19(c)(1) Abatement Verification | Other-than-serious | Jun 11, 2026 | Jun 30, 2026 | $398 | $398 | Final order |
Related
- Massachusetts OSHA citations
- Massachusetts construction citations
- 1926.20 Construction Safety Programs
- 1926.502 Fall Protection Systems
- 1903.19 Abatement Verification
- 1926.150 Construction Fire Protection
- 1926.34 Construction Exit Routes