Florida OSHA citations issued the week of Jan 26, 2026
Week of Jan 26, 2026 · data as of November 16, 2026
57 inspections in Florida had citations issued between Jan 26, 2026 and Feb 1, 2026, with 153 alleged violation items and $834,805 in proposed penalties. Statuses and current penalties reflect the data as of November 16, 2026.
57inspections with citations issued
153alleged violation items
$834,805initial penalties
$707,116current penalties
Alleged violations. Citations are allegations with proposed penalties until they become final orders; each record shows its status label, initial and current penalty as of November 16, 2026. About this data · Methodology
Official records: each osha.gov link opens the official record, next to its inspection number. If osha.gov asks you to verify you're human and then shows its homepage, search that number at OSHA's Establishment Search.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Action Roofing Services, LLC | Stuart | Jan 30, 2026 | 1 | $35,748 | $35,748 | ContestedAbatement due Feb 26, 2026Contested Feb 25, 2026 | osha.gov #348437252 | |
| Action Roofing Services, LLC | Stuart | Jan 30, 2026 | 1 | $35,748 | $35,748 | ContestedAbatement due Feb 26, 2026Contested Feb 25, 2026 | osha.gov #348437534 | |
| Action Roofing Services, LLC | Stuart | Jan 30, 2026 | 1 | $35,748 | $35,748 | ContestedAbatement due Feb 26, 2026Contested Feb 25, 2026 | osha.gov #348437351 | |
| Reworld Lee, Inc. | Fort Myers | Jan 30, 2026 | 2 | $31,446 | $19,861 | Informal settlementAbatement due Feb 26, 2026 | osha.gov #348601709 | |
| Nefco Construction Supply LLC | Orlando | Jan 30, 2026 | 4 | $20,242 | $18,218 | Informal settlementAbatement due Mar 26, 2026 | osha.gov #348639337 | |
| E-Stone USA Corporation | Sebring | Jan 30, 2026 | 2 | $19,861 | $11,917 | Informal settlement | osha.gov #348432535 | |
| Hughes Trim LLC | Tampa | Jan 30, 2026 | 8 | $17,213 | $17,213 | ContestedAbatement due Feb 19, 2026Contested Feb 16, 2026 | osha.gov #348445511 | |
| Azenco US Corp. | Hialeah | Jan 30, 2026 | 2 | $11,585 | $9,268 | Informal settlementAbatement due Feb 26, 2026 | osha.gov #348455528 | |
| O.CT a Common Law Trust | Palm Beach Gardens | Jan 30, 2026 | 4 | $11,352 | $11,352 | Final orderAbatement due Feb 19, 2026 | osha.gov #348458266 | |
| Commercial Concrete Systems, LLC | Naples | Jan 30, 2026 | 2 | $8,512 | $5,107 | Informal settlement | osha.gov #348567488 | |
| Logic Builders, Inc. | North Miami Bch | Jan 30, 2026 | 1 | $2,838 | $2,838 | Informal settlementAbatement due Feb 26, 2026 | osha.gov #348477175 | |
| Blanco Concrete Construction LLC | Delray Beach | Jan 30, 2026 | 1 | $2,838 | $2,838 | Final orderAbatement due Feb 26, 2026 | osha.gov #348588567 | |
| Devastation Store Miami | Miami | Jan 30, 2026 | 1 | $1,702 | $1,702 | Final orderAbatement due Feb 26, 2026 | osha.gov #348715350 | |
| PCP Group, LLC | Largo | Jan 29, 2026 | 8 | $161,344 | $160,866 | Final orderAbatement due Dec 26, 2025 | osha.gov #348296583 | |
| Universal Liquors Enterprises, Inc. | Holiday | Jan 29, 2026 | 4 | $26,481 | $13,770 | Informal settlementAbatement due Feb 25, 2026 | osha.gov #348653312 | |
| Kurasz Construction, Inc. | Lutz | Jan 29, 2026 | 4 | $22,557 | $15,790 | Informal settlement | osha.gov #348512757 | |
| New Service Company | Hialeah | Jan 29, 2026 | 3 | $20,522 | $13,572 | Informal settlementAbatement due Feb 25, 2026 | osha.gov #348411612 | |
| Pike Electric LLC | Middleburg | Jan 29, 2026 | 1 | $16,550 | $16,550 | Informal settlementAbatement due Mar 31, 2026 | osha.gov #348418658 | |
| Clean Step Linens USA, Inc. | Sarasota | Jan 29, 2026 | 4 | $14,754 | $8,852 | Informal settlementAbatement due Feb 25, 2026 | osha.gov #348658329 | |
| Three Brothers Contracting LLC | Oakland | Jan 29, 2026 | 7 | $12,484 | $6,866 | Informal settlementAbatement due Mar 18, 2026 | osha.gov #348701848 | |
| Florida Structural Concrete, LLC | Bradenton | Jan 29, 2026 | 1 | $11,585 | $6,951 | Informal settlementAbatement due Feb 25, 2026 | osha.gov #348529157 | |
| Waltbillig & Hood General Contractors, LLC | Bradenton | Jan 29, 2026 | 1 | $11,585 | $8,689 | Informal settlementAbatement due Feb 25, 2026 | osha.gov #348529215 | |
| Megalodon Marine Construction LLC | Stuart | Jan 29, 2026 | 2 | $7,944 | $7,944 | ContestedAbatement due Feb 25, 2026Contested Feb 6, 2026 | osha.gov #348424318 | |
| Fraga USA, LLC | Dade City | Jan 29, 2026 | 1 | $5,628 | $3,377 | Informal settlement | osha.gov #348662024 | |
| Puleo's Concrete, Inc. | Bradenton | Jan 29, 2026 | 1 | $3,547 | $3,547 | Final order | osha.gov #348529280 | |
| Shaw's Land Clearing, LLC | Orange Park | Jan 28, 2026 | 4 | $15,756 | $15,756 | ContestedContested Feb 17, 2026 | osha.gov #348505736 | |
| Allen Concrete & Masonry, Inc. | Naples | Jan 28, 2026 | 1 | $6,149 | $6,149 | Informal settlement | osha.gov #348429028 | |
| 2nd Century Plumbing, LLC | Naples | Jan 28, 2026 | 1 | $1,929 | $1,447 | Informal settlement | osha.gov #348429093 | |
| Supplyone Tampa Bay, Inc. | Hialeah | Jan 27, 2026 | 1 | $33,762 | $23,633 | Informal settlementAbatement due Mar 30, 2026 | osha.gov #348479726 | |
| APC Construction Services Inc. | Valrico | Jan 27, 2026 | 7 | $26,670 | $16,002 | Final orderAbatement due Feb 23, 2026Contested Feb 27, 2026 | osha.gov #348430398 | |
| Waste Pro of Florida, Inc. | Sanford | Jan 27, 2026 | 2 | $16,550 | $16,550 | Informal settlementAbatement due Mar 17, 2026 | osha.gov #348514613 | |
| Brandon Construction Company General Contractors, Inc. | Tampa | Jan 27, 2026 | 10 | $15,888 | $9,533 | Informal settlementAbatement due Feb 6, 2026 | osha.gov #348639212 | |
| Any Construction Inc. | Land O Lakes | Jan 27, 2026 | 4 | $12,235 | $9,788 | Informal settlementAbatement due Feb 13, 2026 | osha.gov #348674409 | |
| Rhino's Home & Commercial Framing LLC | Treasure Island | Jan 27, 2026 | 7 | $7,944 | $4,766 | Informal settlementAbatement due Feb 6, 2026 | osha.gov #348673559 | |
| SMV Construction Corp. | Land O Lakes | Jan 27, 2026 | 7 | $7,944 | $5,561 | Informal settlementAbatement due Feb 6, 2026 | osha.gov #348674490 | |
| RCB Roofing, LLC | Valrico | Jan 27, 2026 | 2 | $5,676 | $3,406 | Informal settlementAbatement due Feb 23, 2026 | osha.gov #348420514 | |
| Walmart Inc. | Orlando | Jan 26, 2026 | 2 | $17,024 | $8,512 | Informal settlement | osha.gov #348689985 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 2 | $11,348 | $11,348 | Final orderAbatement due Feb 9, 2026 | osha.gov #348673419 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 3 | $11,348 | $11,348 | Final orderAbatement due Feb 9, 2026 | osha.gov #348673401 | |
| Name withheld (individual) | Milton | Jan 26, 2026 | 2 | $10,214 | $10,214 | Final orderAbatement due Feb 9, 2026 | osha.gov #348681230 | |
| G & H Underground Construction, Inc. | Jacksonville Beach | Jan 26, 2026 | 2 | $9,930 | $8,440 | Informal settlement | osha.gov #348658402 | |
| Thrifty Specialty Produce of Rockledge, LLC | Rockledge | Jan 26, 2026 | 1 | $8,513 | $5,108 | Informal settlement | osha.gov #348698390 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 3 | $6,810 | $6,810 | Final order | osha.gov #348673484 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 3 | $6,810 | $6,810 | Final order | osha.gov #348687427 | |
| Name withheld (individual) | Gulf Breeze | Jan 26, 2026 | 3 | $5,675 | $5,675 | Final order | osha.gov #348683988 | |
| Name withheld (individual) | Milton | Jan 26, 2026 | 3 | $5,675 | $5,675 | Final order | osha.gov #348681214 | |
| AL Rock Construction LLC | Niceville | Jan 26, 2026 | 1 | $4,965 | $4,965 | Final orderAbatement due Feb 17, 2026 | osha.gov #348616848 | |
| North Custom Construction Inc. | Freeport | Jan 26, 2026 | 1 | $4,965 | $4,965 | Informal settlementAbatement due Feb 5, 2026 | osha.gov #348612631 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 2 | $4,540 | $4,540 | Final order | osha.gov #348691023 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 2 | $4,540 | $4,540 | Final order | osha.gov #348691031 | |
| Name withheld (individual) | Pace | Jan 26, 2026 | 2 | $4,540 | $4,540 | Final order | osha.gov #348691148 | |
| Name withheld (individual) | Pace | Jan 26, 2026 | 3 | $4,540 | $4,540 | Final order | osha.gov #348687419 | |
| Shaun Bailey Construction LLC | Crestview | Jan 26, 2026 | 1 | $2,837 | $2,837 | Final orderAbatement due Feb 9, 2026 | osha.gov #348593153 | |
| Name withheld (individual) | Crestview | Jan 26, 2026 | 1 | $2,837 | $2,837 | Final orderAbatement due Feb 5, 2026 | osha.gov #348672320 | |
| Protec Powdercoating LLC | Jacksonville | Jan 26, 2026 | 1 | $2,837 | $1,950 | Informal settlementAbatement due Feb 20, 2026 | osha.gov #348642935 | |
| Name withheld (individual) | Milton | Jan 26, 2026 | 1 | $2,270 | $2,270 | Final order | osha.gov #348673567 | |
| Name withheld (individual) | Cantonment | Jan 26, 2026 | 1 | $2,270 | $2,270 | Final order | osha.gov #348691122 |
Standards cited this week
- 1926.501 Fall Protection (28)
- 1926.1053 Ladder Safety (11)
- 1926.102 Eye and Face Protection (11)
- 1926.451 Scaffold Safety (8)
- 1926.503 Fall Protection Training (7)
- 1910.212 Machine Guarding (4)
- 1926.454 Scaffold Training (4)
- 1910.178 Forklifts (4)
- 1910.22 Walking-Working Surfaces (3)
- 1910.303 Electrical General (3)
- Section 5(a)(1) General Duty Clause (3)
- 1904.39 Severe Injury Reporting (3)